Most of our common geomembrane construction is an overall pool that canplay its role. For chemical plants, this cannot meet their usage needs. Just like our tap water treatment plant, sewage needs to remove impurities, which requires a filter pool. After removing impurities, purifying sewage into reclaimed water is another process, which also requires a filter pool. Then converting reclaimed water into drinkable water requires a storage pool. Of course, the above is just an analogy. For chemical plants, they also need to treat wastewater multiple times to meet emission standards, so they also need our good supporting facilities.

The membrane material used this time is 2.0mm thick HDPE impermeable membrane, national standard type. The geotextile used is 500g short fiber geotextile. The welding method used is hot melting, while the connection method of geotextile is thread sewing. For incoming samples and welds, Party A conducted on-site spot checks, and the testing method was witnessed submission for testing.
The total construction duration this time is 90 days. The total construction area is 30,000 square meters for geomembrane and 60,000 square meters for geotextile. There are 20 construction personnel, and the entire construction of the site has been completed.

" />