The Mengding Wogan planting area in Lincang selected two-cloth one-membrane, 1000g thickness composite geomembrane. The total usage area is 2,200 square meters, and the construction period is 5 days. The total time from delivery to construction completion is about 10 days. This is because Mengding is a border town in Yunnan. It takes about 2 days to ship logistics from Kunming, plus transit and personnel allocation on the way, so it took more time.
This site is similar to previous ones. The customer provides relevant power supply and 4-6 personnel allocation. Our side provides 1 technical personnel, among which welding equipment and related auxiliary tools are provided by our company ourselves.
For this site in Mengding, there are many weathered stones and crushed stones in the site. Therefore, before construction, we still required laying a layer of plain soil layer in the site, and performed de-sharpening treatment on sharp stones, so that even if they directly contact the geomembrane, they will not damage the membrane material.

" />